Between 2018 and 2023, the majority of applications to build renewable projects were unsuccessful in progressing through planning. Figures from Cornwall Insight’s Renewables Pipeline Tracker, show that 63% of projects were either abandoned, refused, withdrawn, or ultimately expired.

The data reveals only 20% of projects remain in development statuses that could see projects coming to fruition, meaning they are now at the planning submitted, awaiting construction or under construction stages.

While the overall number of renewables applications has seen a rapid increase, the approval rate remains low, with a growing trend of “non-progressing projects”. No region in Great Britain is currently exceeding a 20% success rate of projects proceeding through planning.

The low success rate of applications has been put down, in part, to an increasingly number of speculative applications being submitted. Industry reports1 show a rise in so called “phantom projects” in these cases, developers submit multiple applications for many sites, with the expectation being that very few will connect. These speculative and duplicate applications have seen the connections queue grow, increasing the work needed to progress projects.

These findings raise concerns about the pace of renewable energy development in Great Britain. Streamlining the grid connections process and addressing speculative applications will be crucial to ensure a more efficient and successful path forward for renewable energy projects.

Figure 1: Status of projects that submitted planning applications between 2018-23

Lucy Dolton, Assets and Infrastructure Manager at Cornwall Insight:

“The UK has set ambitious targets to boost renewable energy capacity. These figures reveal a substantial shortfall in meeting these targets, something which is largely driven by the slow pace of progress in deploying renewable energy projects.

“The total capacity of projects in the grid connection queue is currently well in excess of what is necessary for net zero generation capacity. However, considering the lengthy process for projects to progress through planning and gain grid connections, and the current volume of projects that are unsuccessful, the amount of this capacity that will ultimately connect could be much lower than the pipeline of projects suggests.

“It’s clear that an increasing number of the applications submitted are speculative, raising the numbers in the connections queue, and creating obstacles for projects that are mostly ready to connect.

“It is positive to see the work being undertaken across industry regarding reforming the connections process, addressing grid congestion for both new projects and the existing connection queue. The scale of the challenge is significant, but timely and measured changes will be key for maintaining momentum in the deployment of renewables across the UK.”

Reference:

‘Phantom’ power projects are holding back the UK’s energy security – Centrica report – Ends

Notes to Editors

For more information, please contact: Verity Sinclair at v.sinclair@cornwall-insight.com

To link to our website, please use: https://www.cornwall-insight.com/

Copyright disclaimer for commercial use of the press releases:

The content of the press release, including but not limited to text, data, images, and graphics, is the sole property of Cornwall Insight and is protected by UK copyright law. Any redistribution or reproduction of part or all of the content in any form for commercial use is prohibited without the prior written consent of Cornwall Insight.

Media Use Exemption:

The information included in this press release may be used by members of the media for news reporting purposes only. Any other commercial use of this information is prohibited without the prior written consent of Cornwall Insight.

All non-media use is prohibited, including redistribution, reproduction, or modification of our content in any form for commercial purposes, and requires prior written consent. Please contact: enquiries@cornwall-insight.com

About the Cornwall Insight Group

Cornwall Insight is the pre-eminent provider of research, analysis, consulting and training to businesses and stakeholders engaged in the Australian, Great British, and Irish energy markets. To support our customers, we leverage a powerful combination of analytical capability, a detailed appreciation of regulation codes and policy frameworks, and a practical understanding of how markets function.

"It’s clear that an increasing number of the applications submitted are speculative, raising the numbers in the connections queue, and creating obstacles for projects that are mostly ready to connect."

Lucy Dolton Assets & Infrastructure Manager
footer-background
Get in Touch to Find Out How We Can Support Your Business

Fill in your details and we will get back to you as soon as possible with more information about our solutions.

Get in Touch